土建施工组织设计外文翻译--施工项目成本上升的因素(编辑修改稿)内容摘要:
cs of a project. Many times there is no recognition of the cost drivers operating outside the project’s physical configuration. A joint New York and New Jersey mission in 1918 remended a transportation tunnel under the river “Urges new tunnel under the Hudson.” 1918。 “Ask nation to share in tunnel to Jersey.” 1918. The automobile was emerging as the predominate means of transportation and it was decided that this tunnel should be for vehicular traffic. As a result the tunnel would employ new ventilation technologies to purge the exhaust gases produced by the internal bustion engine. Eleven designs were considered for the tunnel, most notably, one by the engineer recently responsible for finishing the Panama Canal, George Washington Goethals. He envisioned a single, bilevel tunnel with opposing traffic on each level. Goethals made a planning project cost estimate of $12 million and 3 years for construction. World War I had consumed much of the nation’s steel and iron production, so his design made use of cement blocks as the tunnel’s structural shell. His design was the frontrunning plan “Hudson vehicle tube.” but he had responsibilities elsewhere and was not named chief engineer for the project. Clifford M. Holland was named to head the 浙江工业大学之江学院毕业设计(论文) 外文翻译 7 project along with a board of five consulting engineers “Name interstate tunnel engineers.” 1919. Holland came to the project with vast experience in constructing subways and tunnels in New York. The cost of the project was taken to be $12 million, Goethals’ planning estimate. Holland produced a report in February of 1920 based on his analysis of the Goethals’ design of the project. His findings were not what had been expected. Holland found • Goethals’ width of m would not acmodate the volume of traffic. • Concrete blocks would not withstand the structural loads exerted on the tunnel. • The construction methods required by Goethals’ design were pletely untried. • The estimated cost of construction was grossly low. • The work could not be pleted in 3 years. The board of consulting engineers gave unanimous support for Holland’s analysis. Holland then presented a design of his own which was supported unanimously by the consulting engineers. Holland’s design, which was a major scope change, called for twin castiron tubes. One advantage was that construction would follow established methods of tunnel construction that had been implemented for rail tunnels under the East River and further up the Hudson. Holland estimated the cost at $28,669,000 “Asks $28,669,000 for Jersey tube.” 1920 and construction time at 31/2 years. Debate about the tunnel design continued for more than a year creating disagreements between the New York and New Jersey Commissions and delaying the work—a schedule change. A disagreement about awarding a contract on the New Jersey side further delayed the start of construction and added over half of a million dollars in cost. Construction started on the New York side in October of 1920 and in late December 1921 the New Jersey portion of the tunnel was bid “Way all cleared for Jersey tunnel.” The mandated pletion date was December 31, 1926. The construction schedule had now grown to 5 years. Estimated project cost increased multiple times throughout the early years of construction as a result of scope creep, schedule delays, and inflation. Increased traffic forecast necessitate larger entrance/exit plazas and acquisition of more right of way “Vehicular tube is growing.” 1923. Then increases in material and labor costs had added another $6 million to the project inflation. By the beginning of 1924, reestimated costs had been increased by $14,000,000 “Vehicular tunnel cost up $14,000,000.” 1924 due to functional and aesthetic factors scope creep. More intricate roadway designs for approaches, widening of the approach roadways, and architectural treatments increased the costs more scope creep. Redesign of the ventilation system added cm to the tunnel 浙江工业大学之江学院毕业设计(论文) 外文翻译 8 diameter and $4,422,000. Holland also decided to substitute caststeel for castiron to increase the strength and safety factors of the tunnel more scope creep. Last, the New Jersey ventilation shafts had to be redesigned along with their corresponding foundations at a cost of $700,000 due to une。土建施工组织设计外文翻译--施工项目成本上升的因素(编辑修改稿)
相关推荐
表 15 桩号 X 切线高程 y=x2/2R 设计高程 K0+520 0 0 K0+540 20 K0+560 40 K0+580 60 K0+600 80 K0+620 100 K0+640 120 K0+660 140 K0+680 160 K0+700 180 K0+720 160 K0+740 140 K0+760 120 K0+780 100 K0+800 80 K0+820 60
discussed in the paper It is of interest to note that results of the type shown in Fig. 2 have been also found by Bertero39。 in shake table tests of a dual system. DESCRIPTION OF TEST STRUCTURE The
ion per Figure 1/2 minimum diameter anchor bolt and clip angle spaced at 6’ . with 8 8 screws 1/2 minimum diameter anchor bolt and clip angle spaced at 4’ . with 8 8 screws 1/2 minimum diameter
喷射混凝土、锚杆为主要手段)并使围岩与支护结构共同形成支撑环,来承受压力,并最大限度地保持围岩稳定,而不致松动破 坏。 新奥法将围岩视为巷道承载构件的一部分,因此,施工时应尽可能全断面掘进,以减少巷道周边围岩应力的扰动,并采用光面爆破、微差爆破等措施。 减少对围岩的震动,以保全其整体性。 同时注意巷道表面尽可能平滑,避免局部应力集中。 新奥法将锚杆、喷射混凝土适当进行组合,形成比较薄的衬砌层
新版城镇最低收入居民家庭住房保障申请表(表格模板) 申请人 (签章):年 月 日申请人配 偶家 庭住 址联 系电 话现住房产权性质家庭人口 申 请人 关 系性别婚 姻状 况家庭成员经办人: 经办人:负责人: 单位公章: 负责人: 单位公章:说明:申请人单位意见对申请人基本情况的真实性出具审核意见;按照青岛市城镇最低收入居民家庭住房保障管理办法及实施意见的规定 ,提出单位解决意见。
e or axle. The center hexagonal walls are buttressed by the wing walls and hammerhead walls, which behave as the webs and fl anges of a beam to resist the wind shears and moments. Outriggers at the